TIME AND WORK MCQs

A takes twice as much time as B or thrice as much time as C to finish a piece of work. Working together, they can finish the work in 2 days. B can do the work alone in:

  •  (a) 4 days
  •  (b) 6 days
  •  (c) 8 days
  •  (d) 12 days
Check Answer
  •  (b) 6 days

A and B can complete a work in 15 days and 10 days respectively. They started doing the work together but after 2 days B had to leave and A alone completed the remaining work. The whole work was completed in:

  •  (a) 8 days
  •  (b) 10 days
  •  (c) 12 days
  •  (d) 15 days
Check Answer
  •  (c) 12 days

A and B can do a piece of work in 30 days, while B and C can do the same work in 24 days and C and A in 20 days. They all work together for 10 days when B and C leave. How many days more will A take to finish the work?

  •  (a) 18 days
  •  (b) 24 days
  •  (c) 30 days
  •  (d) 36 days
Check Answer
  •  (a) 18 days
Explanation

1. Calculate the individual work rates of A, B, and C:

  • For A and B:
    • A and B together can complete the work in 30 days.
    • Combined work rate of A and B:
      Work rate of A + B = 1/30 of the work per day
  • For B and C:
    • B and C together can complete the work in 24 days.
    • Combined work rate of B and C:
      Work rate of B + C = 1/24 of the work per day
  • For C and A:
    • C and A together can complete the work in 20 days.
    • Combined work rate of C and A:
      Work rate of C + A = 1/20 of the work per day

2. Determine the individual work rates of A, B, and C:

  • Adding all three equations to find A + B + C:
    • (A + B) + (B + C) + (C + A) = 1/30 + 1/24 + 1/20
    • 2A + 2B + 2C = 1/30 + 1/24 + 1/20
    • 2(A + B + C) = 1/30 + 1/24 + 1/20
    • Find a common denominator (120):
      1/30 = 4/120, 1/24 = 5/120, 1/20 = 6/120
    • 2(A + B + C) = 4/120 + 5/120 + 6/120 = 15/120 = 1/8
    • A + B + C = 1/16
  • Therefore:
    • Work rate of A + B = 1/30
    • Work rate of B + C = 1/24
    • Work rate of C + A = 1/20
    • A + B + C = 1/16
    • A = (A + B + C) – (B + C) = 1/161/24 = 1/48
    • B = (A + B + C) – (C + A) = 1/161/20 = 1/80
    • C = (A + B + C) – (A + B) = 1/161/30 = 7/240

3. Calculate the total work done by A, B, and C together in 10 days:

  • Combined work rate: 1/16
  • Work done in 10 days = 10 × 1/16 = 10/16 = 5/8

4. Determine the remaining work and the time A will take to finish it:

  • Remaining work:
    • Remaining work = 1 – 5/8 = 3/8
  • Time taken by A alone:
    • Work rate of A = 1/48
    • Time required = 3/8 / 1/48 = 3/8 × 48 = 18 days

Therefore, A will take:

  • (a) 18 days more to finish the work.

A works twice as fast as B. If B can complete a work in 12 days independently, the number of days in which A and B can together finish the work is:

  •  (a) 4 days
  •  (b) 6 days
  •  (c) 8 days
  •  (d) 18 days
Check Answer
  •  (a) 4 days

Twenty women can do a work in sixteen days. Sixteen men can complete the same work in fifteen days. What is the ratio between the capacity of a man and a woman?

  •  (a) 3:4
  •  (b) 4:3
  •  (c) 5:3
  •  (d) Data inadequate
Check Answer
  •  (b) 4:3

A and B can do a work in 8 days, B and C can do the same work in 12 days. A, B and C together can finish it in 6 days. A and C together will do it in:

  •  (a) 4 days
  •  (b) 6 days
  •  (c) 8 days
  •  (d) 12 days
Check Answer
  •  (c) 8 days

A can finish a work in 24 days, B in 9 days and C in 12 days. B and C start the work but are forced to leave after 3 days. The remaining work was done by A in:

  •  (a) 5 days
  •  (b) 5/6 days
  •  (c) 10 days
  •  (d) 10 × 1/2 days
Check Answer
  •  (c) 10 days

X can do a piece of work in 40 days. He works at it for 8 days and then Y finished it in 16 days. How long will they together take to complete the work?

  •  (a) 13 ⅓  days
  •  (b) 20 days
  •  (c) 15 days
  •  (d) 26 days
Check Answer
  •  (a) 13 ⅓  days

A and B can do a job together in 7 days. A is 1 3/4 times as efficient as B. The same job can be done by A alone in:

  •  (a) 9 × ⅓  days
  •  (b) 11 days
  •  (c) 12 × 1/4 days
  •  (d) 16 × ⅓  days
Check Answer
  •  (b) 11 days

A and B together can do a piece of work in 30 days. A having worked for 16 days, B finishes the remaining work alone in 44 days. In how many days shall B finish the whole work alone?

  •  (a) 30 days
  •  (b) 40 days
  •  (c) 60 days
  •  (d) 70 days
Check Answer
  •  (c) 60 days

You cannot copy content of this page

Scroll to Top